Issue No. 005 Batch Zero August 24, 2026

Texas Is Auditing the Demand. Nobody Is Auditing the Supply.

The data-center audit covers one ERCOT queue. The generation that would have to serve those loads sits in a different queue — and 444 of those requests, about 36% of it, have been open since 2023 or earlier.

Published to subscribers August 24, 2026. Figures are as of that date and are not restated here; current figures are on the homepage.

Two hundred gigawatts of data-center demand is being audited in Texas right now. 326 projects, each asked to prove it is real before it gets a connection.

Not one question in that audit is about where the electricity comes from.


Grid Alpha's argument has always been that an interconnection queue is a record of intentions, not a forecast. Abbott's audit is the first regulatory instrument in the country built on that premise — it assumes the queue overstates itself, and puts the burden of proof on the applicant. We think that is right. We also think it covers one half of the problem, and that the other half is where the risk sits.

Because a data center is a load. It generates nothing. Every megawatt those projects are asking for has to come from a generator that is itself financed, permitted and built — and generators sit in a different ERCOT queue, one nobody has been asked to verify.

Large loads Generation
What they do Draw power Inject power
Projects in the queue 688
Eligible for Batch Zero 326
Demand eligible ~205 GW
Verification target December
Filed 2023 or earlier More than 400
Share of the queue About 36%
Oldest still open 2015
Under the Abbott audit Yes No

Two separate queues, side by side, not a ratio. Large loads: ERCOT presentation to the Senate Committee on Business & Commerce, July 29, 2026, p10 — data as of July 28. December is ERCOT's reporting deadline under PUCT Project 59142, not part of the July 29 deck. Generation: Grid Alpha tracking of the ERCOT GIS Report (Large Gen), pulled August 22, 2026.

The left column is ERCOT's, from its July 29 presentation to the Senate Committee on Business & Commerce. The right is ours, from the generator queue we have tracked since this publication started. Two separate queues — the columns do not divide into each other, and we show them together to make that point, not to imply a ratio.

What the audit actually asks

The August 3 directive is now an operating procedure. ERCOT is running it as two workstreams: Batch Zero Eligibility Verification for large loads of 75 MW and up, which verifies the attestations behind a project's eligibility, and a separate Community Impact Review for computational loads of 25 MW and up, which collects Abbott's List.

What the Community Impact Review does with your answers

Disclosure Collected Eligibility test
Tax incentives received Yes No
Power and water consumption, cooling Yes No
Power source Yes No
Local impact mitigation Yes No
Ownership of the facility Yes No

The five disclosures ERCOT's Community Impact Review collects from computational loads of 25 MW and up. Only the third reaches outside the applicant's own fence.

Read the third line closely. Of the five, it is the only one that reaches outside the applicant's own fence, and it asks for an intention rather than a fact. ERCOT will strike a project from Batch Zero for a materially false eligibility attestation. Naming a generator that never gets built is not one of those attestations.

The queue that has to answer

We track the ERCOT generator interconnection queue — solar, wind, storage, gas. Not data centers. This is the supply side of the same grid, and its defining feature is age.

ERCOT generator interconnection requests without a signed interconnection agreement, by year filed

Year filed Requests
2015 1
2016 1
2017 5
2018 3
2019 23
2020 39
2021 76
2022 100
2023 196
2024 317
2025 325
2026 147

444 of the 1,234 open requests — 36% — were filed in 2023 or earlier. Not one of the 1,234 has signed an interconnection agreement, and 376 of the 444 pre-2024 requests have not completed their interconnection study. 2026 is a partial year, to July 24; one further request carries no queue date and is omitted. Grid Alpha tracking of the ERCOT GIS Report (Large Gen), pulled August 22, 2026.

More than 400 of these requests — about 36% of the queue — were filed in 2023 or earlier and are still open. The oldest still-open request dates to 2015: an eleven-year-old intention to build a power plant, still carried as current.

We want to be careful about what this does and does not prove. "Still open" is not "abandoned" — ERCOT carries a request until the paperwork closes. But not one of these requests has signed an interconnection agreement, and 376 of the 444 filed before 2024 have not yet completed their full interconnection study. That is the population a serious verification regime would be interested in.

Applied to loads, that same screen cut ERCOT's large-load queue from 688 projects to 326 eligible for Batch Zero, and 498 GW to 205. Nobody has run it on the supply side.

What we're watching

The RFIs. Not yet issued. They are the mechanism that produces the first documented Abbott's List failure, and when one lands we name the line it failed on, as committed in Issue #003.

December. ERCOT's target for finishing the audit, against an April 9, 2027 study deadline it says it is still holding.

16 TAC §25.194. Still proposed. The $50,000-per-MW figure is a security deposit — collateral, roughly 80% forfeitable — not a fee, and not law yet.


An audit that verifies demand and assumes supply has cut the problem in half and solved the easier half. If 200 GW of load is real enough to survive Abbott's List, the follow-on question writes itself: which generators, specifically, are going to serve it — and when did they last do anything other than sit in a queue?

We have been keeping that list since before there was an audit.

Why this comes from Grid Alpha

Grid Alpha reads the filings so you don't have to. We tracked 12,677 power projects across the Texas market as of August 14, 2026, and score each one on the questions that decide whether a project gets financed — permits, financing, site control, offtake, ownership — before they make headlines. The live data is at gridalpha.com.

That is the proof line for this issue: the supply-side ledger the audit does not cover is the one we have been keeping all along.

Project count as of August 14, 2026. This is an archived issue; the live count is on the homepage.